Complete Electrical Finishing for 150m Apartment — Heliopolis
A 150m apartment in Heliopolis at the final finishing stage. The owner wanted high-quality electrical finishing with Legrand fixtures, recessed LED lighting, and a Schneider distribution board with full protections.
The apartment was partially finished by a previous contractor with substandard fixtures. We needed to replace all outlets and switches and upgrade the board from just two breakers to a full board with RCD protections.
The recessed lighting design required precise coordination with the interior designer to ensure cable routes aligned with gypsum lines and suspended ceiling grid.
Installed 68 electrical points: Legrand Céliane outlets and lighting scenes
New Schneider iC60N 16-circuit board with RCD and RCBO per circuit
96 recessed LED lights (Philips) in suspended ceilings + bedroom dimmers
Replaced all old outlets and switches with Legrand Céliane white set
Coordinated with interior designer on switch positions before final gypsum installation
Tested each circuit and earth continuity before ceiling and wall finishing
Phase 1
Day 1-2: Inspect existing work, identify replacements
Phase 2
Day 3-6: Board, outlets and switch installation
Phase 3
Day 7-9: Recessed lighting installation and dimmer connections
Phase 4
Day 10: Full test and technical report handover
Delivered on day 10 with zero delays. The owner praised the execution level and organization compared to the previous contractor. The new board handled all loads comfortably with spare capacity for future appliances.
Full one-year warranty on all electrical finishing work.