Ases Kahraba

    Electrical Installation & Finishing Process in Egypt — Step by Step

    An apartment or villa owner who doesn't understand the stages of electrical work falls into one of two traps: rushing the contractor into a rough-in that produces errors visible years later, or being caught off-guard by the timeline and creating conflicts with other trades. This guide explains all six stages from the moment you sign the contract to receiving the handover documents — with realistic durations for each stage and the checkpoints you must stay alert to.

    By the Ases Kahraba team — Last updated: March 2026

    Quick Answer

    A step-by-step guide to the electrical installation and finishing process for apartments and villas in Egypt — all six stages from design to handover, realistic timelines, and the checkpoints you must follow as an owner.

    1

    Stage 1: Design and Planning (1–3 days)

    Before any cable or conduit is touched, an electrical drawing must be produced. The drawing defines the location of every outlet, switch, and lighting point; distributes circuits across the panel; and calculates loads to determine cable cross-sections and breaker ratings.

    What must happen at this stage: — Review the apartment or villa architectural plan with the electrician — Decide the locations of AC units, washing machines, and ovens before work starts — Agree on the number of internet, TV, and CCTV points — Obtain a preliminary load schedule confirming that total capacity matches the unit's supply

    Common error in Egypt: many electricians begin rough-in directly without a drawing. The result: outlets in the wrong locations, cables run in unnecessarily long diagonal routes, and circuits loaded unevenly.

    Time required: drawing for a 120–150m² apartment = one day for the engineer. Multi-storey villa drawing = 2–3 days.

    2

    Stage 2: Electrical Rough-In — Conduits and Cables (3–14 days)

    This stage is the heart of all electrical work. PVC conduits are run inside walls and ceilings, cables are pulled through them, and flush boxes for outlets, switches, and lighting points are fitted.

    Realistic durations: — Apartment up to 120m²: 3–5 working days with a 2–3 person team — Apartment 150–200m²: 5–7 days — Single-floor villa 250m²: 7–10 days — Two-storey villa 350m+ : 10–14 days, or more for pools or generators

    Important for villas: concrete slab conduits must be run before the slabs are poured. If concrete is poured before electrical work is done, the electrician must run conduits through walls instead of ceilings, doubling the work and raising the cost.

    Owner checkpoints during this stage: — Are cables the correct cross-section and from an EOS-certified brand? — Are conduits running parallel and perpendicular inside walls (not random diagonals)? — Are flush boxes fitted flush and secure in the wall? — Is the distribution panel location fixed as agreed and easily accessible?

    3

    Stage 3: Insulation Test Before Wall Closing (half day)

    This stage is skipped in many Egyptian projects — a serious mistake. After cables are run and before walls are plastered, an Insulation Resistance Test must be performed using a Megger on every circuit.

    What the test detects: — Crossed or touching wires inside conduits — Damaged insulation from forced pulling or sharp bends — Incorrect connections inside boxes

    Acceptable result: insulation resistance above 1 megohm for every circuit.

    Why this specific timing? After plastering, the cable is inaccessible without breaking walls. Early detection means a quick, inexpensive repair. Detection after finishing means demolishing part of the apartment.

    Request a written report of the test results — even a handwritten note with the measured figures, signed by the electrician.

    4

    Stage 4: Pause — Coordinating Other Trades (1–4 weeks)

    After rough-in and the insulation test, your project enters a planned electrical pause. This period is necessary and must be scheduled in advance.

    Correct trade order: 1. Electrical, plumbing, and other conduit work finished first (inside walls) 2. Plastering closes the walls 3. Painting 4. Tiling and floors 5. Electrical finishing (the next stage)

    Common error: the tiling contractor starts before the electrician has given final sign-off on cable routes. This happens when the owner pressures the schedule. Result: if the electrician needs to adjust a route after tiling, tiling must be broken.

    Typical duration of this pause: — Apartment: 2–3 weeks (plastering and painting) — Villa: 3–6 weeks (plastering, painting, and possibly exterior work)

    Summer project note: in July and August, high temperatures slow the drying of plaster and paint in lower floors and humid rooms. Add two extra days for this season.

    5

    Stage 5: Electrical Finishing — Outlets, Switches, and Panel (2–5 days)

    Once painting is fully dry, the electrician returns for the final stage: installing outlets, switches, and lighting points; connecting all circuits to the distribution panel; and fitting and labelling the breakers.

    What is done during finishing: — Installing the distribution panel with labelled MCB breakers per circuit — Installing RCD breakers on bathroom and kitchen circuits — Fitting all outlets and switches with earthing connections — Connecting lighting points and chandelier terminals — Installing thermostat controls for AC units if in scope

    Realistic durations: — 120m² apartment: 2–3 days with a two-person team — 180–200m² apartment: 3–4 days — Villa: 4–6 days depending on floors and finishing level

    Finishing checkpoints: — Is the panel from a certified brand (Schneider, Legrand, ABB, Hager)? — Is every breaker clearly labelled with the circuit it protects? — Is there a 30mA RCD on bathroom and kitchen circuits? — Are all outlets firm, flush, and sealed with no gaps in the wall?

    6

    Stage 6: Commissioning Tests and Handover (half day to one day)

    The final stage before acceptance is testing and documentation. This stage must not be rushed.

    Required tests: — Earth Resistance Test: confirms earthing resistance is 2 ohms or less — RCD Test: the test button on each RCD is pressed to confirm instant trip — Sequential circuit commissioning: each circuit is energised in turn to confirm no overload or short — Final insulation resistance test: results compared to the pre-plaster test to detect any deterioration

    Mandatory handover documents: 1. As-Built electrical drawing (records actual routes of every cable and conduit) 2. Earthing resistance test report with measured value 3. Insulation resistance test reports — before and after finishing 4. Panel schedule (every breaker, rated current, circuit it protects) 5. Warranty certificate — duration and what it covers 6. Materials list (cable brand, cross-sections, breaker and outlet brands)

    An electrician who refuses any of these documents is giving you a red flag — do not ignore it.

    Full Timeline Summary — Apartment vs Villa

    Total actual electrical working days (excluding waiting periods for other trades):

    Apartment 100–150m²: — Design: 1 day — Rough-in: 3–5 days — Insulation test: half day — Finishing: 2–3 days — Commissioning tests: half day — Total electrical days: 7–10 actual working days

    Villa 250–350m²: — Design: 2–3 days — Rough-in: 10–14 days — Insulation test: 1 day — Finishing: 4–6 days — Commissioning tests: 1 day — Total electrical days: 17–25 actual working days

    Total project lifespan (including waiting for other trades): — Apartment: 5–8 weeks from rough-in start to key handover — Villa: 10–16 weeks (longer with pool wiring or generator installation)

    Common delay causes in the Egyptian market: — Late material delivery (especially cables and specific branded switches from wholesale warehouses) — Owner indecision on outlet or switch locations — Electrical-plumbing conflict on shared walls — Delays by other trades pushing back the finishing start — Change orders after rough-in has begun (the most common source of extra time and cost)

    Need an Accurate Timeline for Your Electrical Project?

    Ases Kahraba provides an engineering drawing, a detailed project schedule, and documented testing across all rough-in and finishing stages in Cairo, New Cairo, and Sheikh Zayed.

    Call Us Now

    Frequently Asked Questions

    How many days does electrical rough-in and finishing for a 120m² apartment take in Egypt?

    Actual electrical working days: 7–10 days spread across stages (rough-in, tests, finishing). Total project lifespan is 5–8 weeks because electrical work pauses between rough-in and finishing while other trades complete plastering and painting.

    Can I start electrical finishing before painting is done?

    Not recommended. Moisture from fresh paint accumulates in boxes and outlets and accelerates corrosion of connections. Paint can also contaminate the faces of new outlet and switch plates. Wait for paint to dry completely — usually 48–72 hours after the final coat.

    What happens if I skip the insulation test before plastering?

    You risk burying an invisible fault. Touching cables or damaged insulation behind walls typically cause recurring faults, repeated breaker trips, or eventual electrical fire. Repairing the problem after plastering means breaking finished walls — a cost more than ten times what the early test would have cost.

    Why must electrical work precede tiling?

    Because electrical rough-in requires cutting and chasing walls to run conduits and flush boxes. This damages laid tiles. Correct order: electrical and plumbing → plastering → painting → tiling. Any reversal in this sequence generates additional cost.

    What documents must I receive at electrical handover?

    Six documents: (1) As-Built drawing, (2) earthing resistance test report, (3) insulation resistance test report, (4) panel schedule, (5) warranty certificate, (6) materials and specifications list. These documents protect you in any future dispute or when selling the property.

    Can I add outlets or modify electrical work after finishing?

    Yes, but at significantly higher cost because it requires breaking walls. Modification after finishing costs 3–5 times what it would have cost during rough-in. This is why the upfront design stage is so important — every decision made on paper is free; every decision made after plaster costs money.

    When does a villa need two or more distribution panels?

    A villa typically needs two panels when: the total circuit count exceeds 16–18 per panel, there are separate loads for a lower floor and upper floors, or there is an outbuilding (external kitchen, guest house). A villa with a swimming pool usually requires a separate control panel for pumps and heating equipment.